Explain how project management software is used to schedule tasks.
…… [6]
Mark scheme
1 Six from: 6
Define scope of project
Create groups of activities e.g. conception/planning
Create list of milestones
Create list of activities between/to achieve milestones/sequence of activities
Create start and finish dates/lengths of activities
Create lists of dependencies/dependency map of activities/milestones
Carry out critical path analysis to discover shortest/longest time of project
Allows regular updates of project activities/timings
Create charts/Gannt/PERT charts to show project schedule visually
Use of online calendars to organise meetings/workflow/reminders.
A railway company wants to allow customers to book tickets for journeys using its website. A new booking screen will use form controls to collect data about the customer and about the requested journeys. The screen is intended to make it easier for customers to enter the details.
(a) Describe, in detail, three checks that could be carried out on the data as it is collected on the booking screen.
1 ……
2 ……
3 ……
…… [3]
(b) Describe four form controls that could be used on the new booking screen and for each form control describe an appropriate use on the new screen.
…… [8]
(c) Describe the characteristics, other than form controls, of a well-designed data collection screen that make it easier for customers to enter data.
…… [6]
(d) When the booking screen is created it will need to be tested.
Explain the importance of having a test plan.
…… [4]
Mark scheme
2(a) Three from e.g.: 3
Check that data has been entered into the field/box
Check that the data is within pre-set ranges e.g. dates of bookings
Check that the data is in the required format e.g. email address/postal code
Check the data against pre-set values/lookup table of values e.g. title of
customer
Check that the data entered is of the required type.
2(b) Eight from: 8
Four controls from, max two marks per control:
Buttons that can be clicked to activate a task/action
Submit button that sends the form to the dataset/company
Reset button to clear the form so that the customer can start again
Hidden buttons that are not shown/rendered by web browser/are not visible
to users
Carry/send/submit information that is not stored/set by HTML objects/would
be lost when page submitted to server
Checkboxes/on-off switches/toggle boxes (sharing the same name (e.g.
choices of seating/food)) but allow multiple choices to be made
…when checked attribute set the switch is ‘on
…only the ‘on’ state is submitted with form
Radio buttons are mutually exclusive switches (sharing the same name) but
allow only one choice to be made
Radio buttons used to choose/make a choice of e.g. male/female, adult/child
Text input via single line input for e.g. name
Multi-line input for e.g. comments/additional requirements
Authors may create two types of controls that allow users to input text. The
INPUT element creates a single-line input control and the element creates a
multi-line input control. In both cases, the input text becomes the control's
current value
Menus provides (users with) a pre-set list of options from which to choose
Menus used to choose e.g. destination/departure
File select allows the user to select files to submit with a form
Files uploaded e.g. photograph for inclusion on ticket/booking/pass
Controls use the HTML INPUT element to capture user choices/input HTML
SELECT/OPTGROUP/OPTION element creates a menu/TEXTAREA
creates a text input box.
2(c) Six from e.g.: 6
Brevity/concise display/provision of information/instructions with no more
data than is necessary
Simple sentence structure/complete words/affirmative sentences
…no jargon/slang
Consistent format for display of information so user knows where to find/look
for information
Labels should be right-justified and to the left of the input field
Labels should be e.g. capitalised/use a colon to indicate data field
Compatibility with other input screens so that user does not have to
recode/re-enter data
Information/input requests should be in a logical order
Information/input requests should not be repeated.
2(d) Four from: 4
Defines/focuses on/ensures the task/requirements are met
Acts as a guide to/set of instructions for testing the booking screen
Allows management of any changes that are needed during development of
the booking screen
Defines the tests that should be carried out on the booking screen
Records the results of the tests for later analysis/amendment of booking
screen.
(a) Describe the characteristics of incremental prototyping.
…… [4]
(b) Discuss the advantages and disadvantages of incremental prototyping.
…… [8]
Mark scheme
3(a) Four from: 4
Project/model/product is broken into several/many sub
projects/models/products
Model/product is partly built/built on previous iterations
Top priority/essential requirements are produced first and completed
Testing occurs at each iteration/incremental stage
As soon as a requirement is produced/testing is complete, its development
is stopped/goes no further.
3(b) Eight from: 8
Advantages:
Each stage is an identifiable milestone to track progress
Testing is carried out at each incremental stage, allowing faults/problems to
be identified/rectified quickly/before final completion
Testing is easier/quicker because changes are usually small at each
iteration of product
Client/user can see/use new features and review these for any further
changes
Product delivery/completion of early/working versions is faster than other
methods of development
Risks can be managed better since risks are identified and handled during
each iteration/incremental stage
Product delivery/completion of early/working versions can cost less than
other methods of development
Disadvantages:
Incremental/additional changes may affect functionality of earlier versions in
an unexpected manner
May raise problems at the end because all requirements are not
produced/created/identified in product at start
Overall cost of many versions/increments can become exorbitant/excessive.
Must be at least 1 advantage and 1 disadvantage for full marks.
1 mark available for a reasoned conclusion.
Describe how 3D printing would be used when creating objects for use in space exploration.
…… [6]
Mark scheme
4 Six from: 6
Can create/print/manufacture ‘hard-to-build’ objects/objects with complex
geometry for space vehicles/craft/satellites (e.g. rocket nozzles, antennae)
…saves weight/increases strength/rigidity of objects when printed as one
part
Can make designs simpler as no need to take into account the cutting
tools/design create cutting tools
…objects can be created with less bulk, reducing launch costs
Used to create/print/manufacture replacement parts to order
Used to create/print/manufacture specialist tools/medical instruments when
needed
No need to carry a collection of spare parts/tools so saving weight/space
Low volume/one off objects can be created at low cost so reducing costs of
materials and manufacturing, lowering the cost of space vehicles
Models of new designs for space vehicles/parts can be quickly created
Can create lattice structures instead of solid. These have reduced weight
Delicate items can be printed in space to avoid stress of launch
Items can be created and tested as 3D objects with no joins/welds that
might be unsafe/problematic in space.
Computer graphics software can create shapes as vector graphics or as bitmap images.
(a) Identify one use of vector graphics in computing.
…… [1]
(b) Explain, in detail, why vector graphics can be resized without losing image quality but bitmap images usually cannot.
…… [6]
Mark scheme
5(a) One from: 1
Used as outline fonts to describe printable characters/glyphs
Used as scalable graphics/svg in HTML5 on web pages
Used by pen plotters to draw shapes on paper.
5(b) Six from: 6
Vector images use mathematical descriptions/expressions of shapes to
create images
Shapes include lines/polygons/curves/ellipses
Points defined with x-y axes and direction of path
Shapes and positions are recalculated every time the image is resized so
quality is retained
Bitmap images consist of a set number of pixels
When the bitmap is resized, pixels are added/removed/the number of pixels
changes so the quality is altered
Lines in vector images do not get thinner/thicker proportionately when
resized but those in bitmaps do so quality of bitmaps changes.
A chain of supermarkets has a computer system which deals with stock control, payroll, Point of
Sale (POS) terminals and a customer database. The computer system is to be replaced with a new system.
Analyse the suitability of using phased implementation in this situation.
…… [8]
Mark scheme
6 Eight from: 8
Changeover takes place in stages by replacing one part/area then another
Parts of the old system are used alongside/with newly installed parts
Costs of implementation can be spread over time as all hardware/software
is not installed at once
New systems can be used alongside old ones/form of parallel running with
same stock control system to check suitability/functionality
If (one/individual) new POS system does not work properly old ones can be
used to avoid customer dissatisfaction at sales points
Staff/user training can be carried out in stages by rotating staff around
departments/areas
…with trained staff assisting those being trained
Staff/users can be familiarised slowly/gradually with new system and see
how it works while using old one
If new POS system fails at checkout there is no backup/alternative available
other than to move to an old POS system at another checkout with
accompanying customer dissatisfaction
Complete changeover of all POS systems will take much longer than e.g.
direct changeover of all POS systems
Disruption to checkouts will be longer/more intensive than e.g. direct
changeover of all POS systems.
Describe how peer-to-peer file sharing can be carried out using the BitTorrent protocol.
…… [6]
Mark scheme
7 Six from: 6
Multiple servers/source computers can be/are used without a central server
BitTorrent client required on internet-connected computer to implement
BitTorrent protocol
Protocol works well/effectively over low-bandwidth connections
BitTorrent descriptor file is used to describe file being distributed
BitTorrent node set up with use of descriptor file and file to be distributed
Node becomes seed for download
Files made available to others for download by connection to seed/other
peers
File being distributed is divided into small segments/pieces
Segment/piece becomes available to other peers as it is downloaded
…original seed/source is relieved of load
Every segment/piece is encrypted/protected by a cryptographic hash that
can be used to detect changes to ensure file integrity
Segments/pieces downloaded in random order/non-sequentially and re-
ordered by BitTorrent client.
Evaluate, by weighing up the advantages and disadvantages, the use of wireless communications in the home.
…… [8]
Mark scheme
8 Eight from e.g.: 8
Enables distribution of internet/network traffic/television and radio signals
around home
Allows (remote) control of devices/TVs/devices without the need for wired
connections
Allows use of multiple wireless handsets to use one wired landline so no
need for extra lines/connections to landline
Allows use of wireless doorbells without damage to infrastructure of
building/doors
Allows communication without disruption/unsightliness of wires so can be
used in historic buildings
Allows multiple devices to connect to central points/internet access points so
no need for additional internet connections/ISPs
Allows easy sharing of devices/printers/scanners between computers so no
need for complex configuration/setup routines/installations
Allows devices to be moved around/mobility of devices while in use so user
can work anywhere
Allows use of (discrete) hearing aids connected to e.g. TV sets so no need
for embarrassment of user/high sound volumes that disturb others
Allows use of remote control/monitoring of household appliances when
away from home
Allows remote placement of security devices/cameras to avoid
tampering/revealing placement position
Can be subject to interference from electronic devices/microwave
ovens/fridges so can prove unreliable
Can create security issues if not set up properly so users’ personal
information can be at risk.
Must be at least 1 advantage and 1 disadvantage for full marks.
One mark available for reasoned opinion/conclusion.
In JavaScript, conditional statements can be used to carry out specific actions based upon different conditions. The value of the variable ‘age’ is entered into a web page and collected by the HTML code of the page. The function in Fig. 9.1 uses the ‘if else’ and ‘else if’ conditional statements to test the value of the variable ‘age’. Line numbers are shown only for your convenience when referring to the code.
1 function myFunction() {
2 var statement;
3 var age = document.getElementById("age").value;
4 if (age < 10) {
5 statement = "You are not old enough to go to this school";
6 } else if (age < 18) {
7 statement = "You can go to this school";
8 } else {
9 statement = "You are too old to go to this school";
10 }
Fig. 9.1
(a) Explain, with reference to the code in the function, how the ‘if else’ and ‘else if’ statements operate to provide the appropriate statement when an age is entered into the web page and collected by the HTML code.
…… [6]
(b) The code could have been written using the ‘switch’ function, e.g. lines 4 to 7 could have been:
4 switch(true) {
5 case age < 10:
6 statement = "You are not old enough to go to this school";
7 break;
with additional lines for the other conditions.
Explain the drawbacks of using the ‘switch’ function.
…… [4]
Mark scheme
9(a) Six from: 6
If statement specifies block of code that is executed if a condition is TRUE
Line 4 if statement compares ‘age’ with condition <10
if TRUE ‘You are not old enough…’is stored in variable ‘statement’
if FALSE execution is passed to line 6
Else-if statement specifies a new condition to be checked if the first
condition is FALSE
Line 6 else if statement compares ‘age’ with condition <18
if TRUE ‘You can go to this school’ is stored in variable ‘statement’
if FALSE execution is passed to line 8 and "You are too old to go to this
school" is stored in variable ‘statement’
Else statement specifies the code to be executed if condition is FALSE.
9(b) Four from: 4
The order of Case/conditions checks in code must be logically
correct/perfect
…for correct /expected comparisons to be made
(Switch) syntax does not follow the usual rules/colons not semi-colons so
code is difficult/confusing to write/read
Code can be lengthy as each condition has to be individually stated
…this is repetitive and prone to error
‘break’ has to be manually inserted after every ‘case’
….debugging problems/difficulties with ‘nested’ conditions
’default’ condition should be included to catch/trap unexpected conditions.
Evaluate, by weighing up the advantages and disadvantages, the impact of image editing in the making of movies.
…… [6]
Mark scheme
10 Six from e.g.: 6
Adding visual special effects/computer-generated imagery (CGI) to video
sequences allows for creation of images that cannot exist in reality/enhance
the entertainment value
Colourising monochrome/black and white film stock to increase acceptability
to audiences/sales of old films
Images can be improved/changed by altering colours/shades/hues to
influence viewers
Images can be altered to remove/include objects/people not in original
scene to influence/mislead viewers
Images of impossible objects/situations can be created
Altering photographic images to enhance sales of products can mislead
buyers
Altering photographic images to people to enhance appearance can mislead
fans.
Must be at least 1 of each for full marks.
Checked your answers against these? Let AI mark the whole paper, on your own working.
Examiners follow the generic marking principles at the front of the scheme, then each question's points: method (M), accuracy (A) and independent (B) marks, error carried forward where the scheme allows it, and positive marking, so you're credited for what you got right.
Check your answers against it
Done this paper? Upload your script and CIE Buddy's AI marker marks it question by question against this exact scheme, puts the ticks on your own working and says what each lost mark needed.
Where can I find the 9626/32 February/March 2020 mark scheme?+
On this page, free: the mark scheme for AS & A Level Information Technology 9626/32, February/March 2020 (9626_m20_ms_32), and the question paper (9626_m20_qp_32), to read or download, with each question's marking points written out underneath.
How many marks is 9626/32 out of?+
Information Technology 9626/32 for February/March 2020 is out of 90 marks, with 1 hour 45 minutes to answer it.
Can I get my 9626/32 answers marked?+
Yes. Upload your answers to 9626/32/F/M/20 as a PDF or photos, and CIE Buddy marks every question against this paper's official mark scheme, using Cambridge's marking rules. You get your score, each lost mark explained on your own script, and the topics to revise. It's a guide, not an official Cambridge grade.