Every Saturday, a particular community holds a ‘Puzzle’ event to raise money for a new Leisure Centre.
Competitors attempt to solve a puzzle as quickly as possible.
Last Saturday, 600 competitors took part. The times taken to complete the puzzle were normally distributed with mean 32.4 minutes and standard deviation 2.5 minutes.
(a) How many competitors would you expect to have times within 1.2 minutes of the mean time? [4]
In this Saturday’s event, 60% of the competitors had times less than 36.0 minutes.
(b) 9 competitors who took part in this Saturday’s event are selected at random.
Find the probability that at least 2 and fewer than 8 of these competitors had times less than 36.0 minutes. [3]
(c) 80 competitors who took part in this Saturday’s event are selected at random.
Use a suitable approximation to find the probability that more than 50 of these competitors had times less than 36.0 minutes. [5]
Mark scheme
4(a) −1.2 1.2 M1 OE
P( <Z < )
2.5 2.5 Using ± standardisation formula, not σ 2 , not σ, no continuity
correction
Use of ±standardisation formula once with 32.4, 2.5 and either
31.2 or 33.6. No continuity correction, not σ 2 , not σ
1.2 1.2
Implied by either − or seen
2.5 2.5
[= Φ ( 0.48) + Φ ( −0.48) = 2Φ ( 0.48 ) − 1 ] M1 Calculating the correct probability area (leading to their final
2 × 0.6844 – 1 or 2 × (0.6844 – 0.5) or 0.6844 – 0.3156 probability).
This may be implied by the correct or appropriate probability area.
0.3688 A1
Expected number = 0.3688 × 600 = 221.28 so 221 or 222 B1 FT FT their 4-figure probability to obtain a single integer answer. No
approximation indicated, condone use of 3sf probability here if
more accurate answer seen earlier.
4
4(b) Method 1
[P(2 ⩽ X < 8) = 1 – P(0, 1, 8, 9) = ] M1 One term of the form 9Cx ( p ) x (1 − p )9− x , 0 < p < 1, x ≠ 0 or 9
1 – (0.49 + 9C1 0.48 0.6 + 9C8 0.410.68 + 0.69) =
A1 Correct un-simplified expression.
Condone omission of last bracket only. If both brackets omitted in
[1 – 0.000262144 – 0.00353894 – 0.060466176 – 0.010077696 =]
un-simplified expression, allow recovery for final stated
calculation of 1 – 0.07434… or better.
0.926 B1 0.925 < p ⩽ 0.926 from correct working.
Method 2
[P(2 ⩽ X < 8) = P(2, 3, 4, 5, 6, 7) = ] M1 One term of the form 9Cx ( p ) x (1 − p )9− x , 0 < p < 1, x ≠ 0 or 9.
9
C2 0.47 0.62 +9C3 0.46 0.63 +9C4 0.45 0.64 +9C5 0.44 0.65 +9C6 0.43
A1 Correct un-simplified expression.
0.66 +9C7 0.42 0.67
0.926 B1 0.925 < p ⩽ 0.926 from correct working.
3
4(c) Mean = 80 ×0.6 = 48 B1 48 and 19.2 (CAO) seen, allow un-simplified.
Variance = 80 × 0.6 × 0.4 = 19.2 May be in standardisation formula.
(4.38178… to at least 4SF identified as σ implies correct
variance).
Do not condone clear incorrect identification.
50.5 − 48 M1 Substituting their 48 and their 19.2 into the ±standardising
[P(X > 50 ) =] P( Z > ) formula (any number for 50.5), allow σ2 or √σ.
19.2
M1 Use continuity correction 49.5 or 50.5 in their standardisation
formula.
2.5 2.5
Note: If no working ± or ± 4.382 seen gains B2.
19.2
[P( Z > 0.571 ) = 1 − Φ ( 0.571) = ] M1 Appropriate probability area, from final process, must be a
1 – 0.7160 = probability.
May be implied by a sketch of the required probability area.
Expect final answer < 0.5.
0.284 A1 AWRT